Lab Schedules |
2016 CLP Available |
|
|
|
|
Summer Session Course Accepted by Campus |
|
|
|
12/4/15 (b) |
BELS requests lab schedules from instructors |
7/1/15 |
10/18/15 |
11/1/15 |
|
Proposed Lab Schedules Due to BELS |
3/25/15 |
7/30/15 |
11/20/15 |
|
Schedule to Registar's office |
3/26/15 |
8/1/15 |
11/25/15 |
|
Lab Schedule Corrections Due to BELS |
4/25/15 |
10/22/15 |
2/4/16 |
|
Corrected proofs due to Registar's Office |
5/01/15 |
10/23/15 |
2/5/16 |
|
Schedule of Classes Posted to Web |
5/11/15 |
11/02/15 |
2/16/16 |
Fri 4/1/16 |
Students begin enrollment |
5/18/15 |
11/09/15 |
2/24/16 |
Sun 5/1/16 |
=============================== |
======== |
======== |
======== |
======== |
ITS Campus Computing Lab Reservations Deadlines (see Note A)
|
|
|
|
|
ITS Computing Lab Reserv Cutoff #1 |
2/18/15 |
6/24/15 |
10/21/15 |
(see Note B) |
ITS Computing Lab Reserv Cutoff #1 |
4/2/15 |
9/30/15 |
1/14/16 |
(see Note B) |
ITS Computing Lab Reserv Final |
5/22/15 |
11/20/15 |
2/18/16 |
(see Note B) |
ITS Computing Lab Final Scheuled Posted |
early 6/15 |
early 12/15 |
end 2/16 |
|
=============================== |
======== |
======== |
======== |
======== |
BELS Lab Support Requirements |
|
|
|
|
Lab Fees Due to Registar |
|
|
|
|
BELS issue request for lab requirements (120 days prior to instruction)
|
6/1/15 |
9/1/15 |
12/1/15 |
|
Instructors - Lab Requirements due to BELS (90 Days Prior to Instruction)
|
7/1/15 |
10/1/15 |
1/1/16 |
|
BELS - inventory existing material (80 days prior to instruction) |
8/1/15 |
10/13/15 |
1/11/16 |
|
BELS - Order additional material & supplies (70 days prior to instruction) |
8/15/15 |
10/20/15 |
1/21/16 |
|
BELS - assemble lab kits (45 days prior to instruction) |
9/1/15 |
11/10/15 |
2/13/16 |
|
BELS request software lists from instructors (30 days prior to instruction) |
9/1/15 |
11/15/15 |
2/27/16 |
|
BELS - Computer Master Images Due (15 work days prior to instruction) |
9/15/15 |
12/1/15 |
2/27/16 |
|
Campus - Prior Quarter End |
9/14/15 |
12/10/15 |
3/17/16 |
|
BELS/Facilities - Close Labs for turnover/remake |
9/14/15 |
12/11/15 |
Fri 3/18/16 |
|
BELS - Clean/Retool labs, install new/revised computer images
|
|
7 days holidays |
4 days |
|
Campus - Instruction Start |
9/24/15 |
1/4/16 |
3/28/16 |
Session 1: 6/20-7/22 Session 2: 6/25-8/26 8 Week: 6/20-8/12 10-Week: 6/20-8/26 |
BELS - Labs ready for use (target) |
|
|
|
|
BELS - Distribute Course Materials |
|
|
|
|
Quarter Enrollment Snapshot |
|
|
|
|
Campus -Finals Week |
12/7-10/15 |
3/14-17/15 |
6/6-9/15 |
|
Labs Close |
Fri 12/11/15 8am |
Fri 3/18/15 (except Sr Design)
|
6/10/15 |
|
Campus - Curtailment/Closure |
TBD |
12/24-1/1 |
TBD |
|
|
|
Campus reopens 1/4 |
|
|